Langley Park Primary School

Convert existing library into 2 classrooms

APPROACH

Firstly line the apex roof with security mesh and breathable membrane, allowing no debris or moisture to escape into the ceiling void.
Install 70mm metal stud partition to create the classroom divide, board using sound shield plasterboard to minimise sound traveling from one room to the next, skim finish.
Install new 600 x 600 suspended ceilings in new classrooms.
Fit new Modular LED lighting to both classrooms, accompanied with individual light switches and 2 double sockets for each room.
Install new skirting, door frames and doors
Paint all internal walls and woodwork
Screed all areas in preparation for new flooring
Install new carpet tile flooring